6-12
Storage Manager
Click the Defaults button to set the Battery Capacity Warnings to their
default values. Actual default values are calculated by the controller based
on the size of the cache memory.
BB4050 Battery Status Messages
Battery Module status is reported as one of the following:
Full
The battery is fully charged.
Charging
The battery is charging after being
partially or fully discharged.
Initial calibration charge
The battery is in the first phase
(charging) of the initial calibration
cycle.
Initial calibration discharge
The battery is in the discharge
phase of the initial calibration
cycle.
Initial calibration recharge
The battery is in the final phase
(recharge after discharge) of the
initial calibration cycle.
Maintenance calibration discharge
The battery is being discharged as
part of the maintenance cycle.
Maintenance calibration charge
The battery is charging as part of
the maintenance cycle.
Initial Calibration (BB4050)
The Initial Calibration operation is started when a BB4050 Battery Backup
Module is first installed on a controller. This function ensures the battery
is fully charged for subsequent backup operation. The calibration cycle
requires approximately 24 hours to complete. The BB4050 module will not
be able to provide backup capability during this operation. When the
process is completed, the BB4050 module is ready for normal operation.
This function has three phases:
1. Initial charge: The battery is charged to its full capacity.
2. Discharge: The battery is discharged until no backup capacity
remains.
3. Recharge: The battery is recharged to full capacity.